Project Schedule and Phases

  2002 2003
Task Description Start End S O N D J F M A M J J A S O N D
Task 1: Project Orientation 09/02/02 10/02/02                                
Task 2: Inventory Existing Plans 09/02/02 03/02/02                                
Task 3: Public Planning Team 10/02/02 09/03/02                                
Task 4: Community Forum # 1 and Outreach 03/03/02 04/03/02                                
Task 5: Concept Plan Development 04/03/02 06/03/02                                
Task 6: Community Forum #2 and Outreach 06/03/02 08/03/02                                
Task 7: Prepare Final Master Plan and Costs 08/03/02 09/03/02                                
Task 8: Prepare Capital Improvement Plan 09/03/02 11/03/02                                
Task 9: Quarterly Reporting and Invoicing 01/03/03 12/02/03                                

Project Team

Project Meetings